Project: York St John University Client: Kier Construction Value: £700,000.00 Completed: Ongoing
BWS have just been awarded the SFS, Metal awarded the Drylining and Ceilings package on this prestige fast track programmed project for Ikea using our flexibility to deliver such a large project in a tight timescale.
Our works commenced in May 2017 which involved forming Jumbo Stud Partitions to divide the warehouse from the retail floors, along with Metal Stud Partitions, Ceilings and MF Bulkheads to form the retail and Café areas
BWS with the help from Knauf developed a Drywall solution, suitable for the challenges of the programme and achieve the best value scheme for our client.
The project was delivered on time and budget on one of Clugston’s largest projects.